JUNIPER
RIDGE PROJECT
November 23, 2009
Construction start: October
6, 2009
Two Main Phases: 13,500
linear foot 9’ diameter steel penstock (pipe)
[Contractual
completion date – April 2, 2010]
5.0
Megawatt hydroelectric facility
[Contractual
completion date – October 6, 2010]
SUMMARY
The purpose of this summary is to highlight the major
items associated with the Juniper Ridge Project’s construction. The Juniper Ridge Project has many components
of construction or activity that is fully detailed in the accompanying Gantt
chart. The Gantt chart has scheduled
start and end dates associated with each activity and a progress to date
bar. The project Gantt chart is updated
at the end of every month and the October 27, 2009 chart is attached to this
summary.
At this point, all construction, procurement, design and
regulatory permitting activities and tasks are on schedule.
Design –
All structural, mechanical and civil design items are completed. Electrical design for the facility and
interconnection is completed. The
Facilities Study has been completed with PacifiCorp and the last remaining
items of clarification pertaining to which entity constructs which pieces of
the interconnection are currently being determined and negotiated with
PacifiCorp. COID has formally notified
PacifiCorp that it will be completing the interconnection process under Oregon
PUC rules of the recently finalized and enacted AR-521 docket. AR-521 provides for the opportunity of having
certified third parties do more of the interconnection work versus PacifiCorp
work crews. Working with third party
contractors provides the benefits of a contractually binding performance
schedule and generally lower expense.
Previous to AR-521, PacifiCorp would do more of the interconnection work
but only on an expense estimate and best efforts of construction with no
binding commitment that work would be performed as necessary for the
project. Moving the interconnection
process over to AR-521 does not effect the project schedule and keeps the
project in its same spot on the PacifiCorp que for implementation.
The Interconnection agreement is expected to be signed by
mid-December, 2009.
Permits –
There are only three specific “permits” that are required in order for the
project to be completed and are relatively symbiotic to one another. All “permits” are on schedule for issuance in
line with the project schedule:
·
FERC Conduit Exemption
o
Application submitted and processed by FERC
(P-13607). FERC has publicly noticed on an expedited basis with issuance of the
Exemption anticipated on December 27, 2009 or shortly thereafter.
·
OWRD water right issuance
o
Application already pending and to be issued
by mid-December 2009.
·
Building Permit from
o
Site
Plan Application submitted in September 2009.
The only comments received were from the City of
o
o
Building Permit issuance is dependent on
issuance of FERC Conduit Exemption and OWRD Water Right. As long as received by
mid-January there will be no effect the project schedule as that is when
construction of all above ground items needs to occur.
Procurement
– All
items for the Project have been ordered, completed, or under fabrication on
schedule including all electrical, mechanical, generator and turbine. The detailed listing of items are in the
accompanying Gantt chart.
Penstock
– Excavation,
pipe placement and trench filing are on schedule. Crews have been averaging 6 pieces of pipe
placement per work day and the schedule requires 4 pieces of pipe per work
day. Welding of the pipe joints is also
on schedule.
Tailrace
& By-Pass Structure – Excavation and below ground concrete
pouring currently underway per schedule.
Valve placement and vault structure on schedule to begin in later
January/early February. This is a
critical item to be completed on time as the irrigation season begins in early
April and liquidated damages to the contractor kick in if the project does not
begin to pass water thru the canal.
Intake
Structure – Excavation has begun with concrete structural work
scheduled to begin in early December
Powerhouse –
All civil work for the site has begun on schedule and it proceeding on
time. Below ground work and construction
has received permission from
Report prepared by:
Steven
C Johnson