MANAGER’S REPORT
9 February. 2010
The
El Nino winter weather is shaping up as one providing a fair amount of moisture
in the lower elevations but a below average snowpack. Last estimates are showing 65-75% of average
moisture content levels. A below average
snowpack will result in lower natural flow water flows in the Deschutes and
tributaries and therefore lower supply for all irrigation district water
rights. This will result in heavier
reliance on storage water in the reservoirs to fulfill demand. This then carries over into the need of next
winter needing to provide above average snowpack so the reservoirs can fill and
likely provides for lower water levels in
The Juniper Ridge Project continues to be on schedule and on budget. All 13,750’ of 9 foot diameter steel pipe is anticipated to be completed in mid-February. This leaves the completion of the inlet and outlet structures for the beginning of April for irrigation season. The contract is structured for heavy penalties to be incurred by the contractor if not completed on schedule. At the present time the risk is minimal for this to occur.
At
the completion of January’s stock water run on the
The US Fish & Wildlife Service issued its draft Critical Habitat Plan (CHP) for Bull Trout. The new CHP was prepared in response to legal challenges of the last CHP finalized in 2005. The CHP areas identified were:
· the entire Metolious sub-basin
·
the
·
the
o
Whychus Creek from its confluence with the
There
were not any significant changes between the new draft CHP and the prior plan
for the
The Oregon Legislature began its special one month session on Monday, February 1. COID and the OWRC will track bills of interest or concern in the coming weeks. COID is actively engaged on a few bills involving hydroelectric development, the Business Energy Tax Credit and eligibility criterion for the Oregon Renewable Portfolio Standard.
Opportunities
· The DBBC plans on submitting appropriation requests to the Congressional Delegation for additional federal funding of the Bureau of Reclamation’s Deschutes Project line item. Funding has successfully been increased by several hundred thousand dollars in each of the last two years and utilized by COID and the other irrigation districts in the DBBC for conserved water projects.
·
COID along with NUID and Swalley are conducting
negotiations with two energy companies interested in implementing small scale
hydro at the North Canal Dam in
· The Habitat Conservation Plan is continuing under an extension of its existing grant from the US Fish & Wildlife Service through Oregon Dept of Fish & Wildlife. A grant application for roughly $400,000 of HCP funding was filed and an announcement of award is expected in the spring of 2010.
·
·
·
COID and BLM have begun the anticipated two year
process to complete the land swap authorized by Congress in the public lands
bill passed this year in Badlands area east of
·
COID has re-engaged Pacific Power in
conversations over termination of their lease and hydro facility at
Challenges
STATUS REPORT
Juniper
Ridge Piping & Hydroelectric Project
· See separate Project Update report
Real
Estate
· One 20 acre
parcel near
Status – In Process with no change in last month
· COID and
the
Status – Paused. No joint meetings have been conducted with
City of
·
A Conditional
Use permit was received for COID owned lands along
Status – In Process with no change in last month
Development
· Direct communication with City of Bend and Redmond public works and planning staff on resolving issues of canal safety and impacts of development that will require piping. Successful coordination and planning on Odem-Medo improvements most recent example of effort.
Status – Ongoing.
ON THE RADAR SCREEN
·