MANAGER’S REPORT
9 March. 2010
The
winter is almost over and irrigation season will begin in April. The snowpack is at 56% moisture content to
average but both Wickiup and Crane Prairie Reservoirs will be full. The below average snowpack will diminish natural
flows in the
The Juniper Ridge Project continues to be on schedule and on budget. All 13,750’ of 9 foot diameter steel pipe is installed with only the remaining tail race and inlet structures to be completed before irrigation season. Testing of the pipeline with intermittent water flows will begin the first week of April and it is anticipated that irrigation season with uninterrupted flows will occur around April 8th. During irrigation season the hydroelectric facility will still be under construction but is scheduled to become fully operational and deemed commercial this fall.
The repairs to the canal bottom collapse on the Central Oregon Canal were completed in time for the scheduled stock run last month and analysis of the repairs after the stock run were very positive. The pending water run along with the stock run in March will provide an additional test on the repairs and an evaluation of the integrity of the canal for the coming irrigation season.
The Oregon Legislature concluded its special one month session and passed two bills that were of particular interest to COID and both are anticipated to be signed by the Governor.
The first bill passed now allows the Siphon Power Plant to be eligible to participate in the Oregon Renewable Portfolio Standard and if certified will be allowed to market/sell Renewable Energy Credits. This is a very positive outcome that could generate additional revenues to COID.
The second bill involved changes to the structure of the State’s Business Energy Tax Credit Program. While significant changes were made to adjust and lower the State’s general revenue impacts there was minimal change to the pre-certified status COID received for the Juniper Ridge Project. Any new hydro plants pursued by COID will fall under the new statutes passed by the Legislature.
Opportunities
· The DBBC submitted appropriation requests to the Congressional Delegation for additional federal funding of the Bureau of Reclamation’s Deschutes Project line item. Funding has successfully been increased by several hundred thousand dollars in each of the last two years and utilized by COID and the other irrigation districts in the DBBC for conserved water projects.
·
COID along with NUID and Swalley are conducting
negotiations with two energy companies interested in implementing small scale
hydro at the North Canal Dam in
· The Habitat Conservation Plan is continuing under an extension of its existing grant from the US Fish & Wildlife Service through Oregon Dept of Fish & Wildlife. A grant application for roughly $400,000 of HCP funding was filed and an announcement of award is expected in the spring of 2010.
·
·
· The Deschutes Water Alliance (DWA) conducted its second public meeting with stakeholders from all irrigation districts, cities, counties, the Confederated Tribes of Warm Springs, the Deschutes River Conservancy and various other state agencies were in attendance. Discussion and presentations focused on particular water concerns and addressing questions raised at the first DWA meeting.
·
COID and BLM have begun the anticipated two year
process to complete the land swap authorized by Congress in the public lands
bill passed this year in Badlands area east of
·
COID has re-engaged Pacific Power in
conversations over termination of their lease and hydro facility at
Challenges
STATUS REPORT
Juniper
Ridge Piping & Hydroelectric Project
· See separate Project Update report
Real
Estate
· One 20 acre
parcel near
Status – In Process with no change in last month
· COID and
the
Status – Paused. No joint meetings have been conducted with
City of
·
A Conditional
Use permit was received for COID owned lands along
Status – In Process with no change in last month
Development
· Direct communication with City of Bend and Redmond public works and planning staff on resolving issues of canal safety and impacts of development that will require piping. Successful coordination and planning on Odem-Medo improvements most recent example of effort.
Status – Ongoing.